Thursday, September 27, 2012

The Number 1 US Nuclear Safety Concern ==> San Onofre's Replacement Steam Generators




The DAB Safety Team is thankful to numerous anonymous concerned SONGS Workers, who have provided factual information in the interest of the Public Safety to us so that we could arrive at these “Reasonable Conclusions” regarding SONGS Replacement Steam Generators Degradation.  We acknowledge Fairewinds Energy Association, Professor Daniel Hirsch, Friends of the Earth, San Clemente Green, Media, News Papers and the SD Reader, whose material has contributed to the successful completion of this document.
NOTE: These Preliminary Conclusions are subject to change upon receipt of Southern California Edison's (SCE) SONGS Unit 2 Restart Plan and Mitsubishi Heavy Industries (MHI) Root Cause Evaluation.
 
If SONGS Unit 2 is allowed to operate at reduced power, an Un-isolable main steam line break accident can occur at any time, due to a postulated design basis earthquake and/or any other associated failure.  Due to this event, the depressurization of the steam generator caused by the steam line break coupled with the excessive vibrations due high differential pressure (> 2250 psi), high reactor coolant water temperature inside the tubes, the compact space between the SONGS U-Tube Bundle and the moisture separators (compared with other Mitsubishi Steam Generators) and the steam over-pressurization would cause the elastic deformation (NRC AIT Report, Mitsubishi Preliminary Cause Evaluation) of the taller U-tube bundle due to increased U-tube bundle height, high localized steam-voids or dry-outs (two-phase mist region, almost devoid of water in undefined central portion of the U-tube bundle above the 7th support plate) and narrow-pitch/tube diameter ratio.  This unanalyzed and rare phenomena not experienced in the Steam Generators operating history, in turn, would cause the onset of fluid elastic instability conditions due to the 100% localized steam voids in the central portion of U-Tube bundle above the 7th Support Plate.  The fluid elastic instability conditions would result in further lowering the already low in-plane tube clearances (Attributed to unanalyzed effects because of addition of more tubes to achieve more thermal MWt out of the SGs). The combination of these factors along with a poorly designed anti-vibration support structure [low damping capability of the support structure (i.e., the tube support plates, the tube-sheet, and the anti-vibration bars)] would result in excessive and violent vibrations, cause tubes to hit each other in the in-plane direction, result in leaking tubes, which would cause high-pressure primary sub-cooled water jets.  These high-pressure jets would cut holes into other already worn tubes and create undetermined number of cascading tube ruptures.

The cumulative effects of the above conditions along with the unanalyzed effects of plugged and staked tubes would rupture other damaged, plugged, staked and worn tubes.  The amount of leaking reactor coolant through these ruptured tube cuts is beyond the analyzed limits of a SONGS UFSAR Analysis [Three combined independent events loads (DBE + MSLB + LOCA)] that would be released via the blowing radioactive steam carrying Un-partitioned reactor coolant from the Un-isolated steam generator into the environment.  This uncontrolled radiological accident would release significant amounts of radiation, which could adversely affect the health and safety of all Southern Californian residents plus the transient population within the 10-mile Emergency Planning Zone.   We believe that this scenario can also progress into a nuclear meltdown of the reactor due to potential errors by plant operators unable to diagnose and control rapidly changing plant conditions due to the confusion caused by the non-user friendly and complex, abnormal, emergency operating and emergency plan implementing procedures.  

This scenario is a departure from a method of evaluation described in the UFSAR used in establishing the SONGS design bases or in the safety analyses and requires a NRC 50.90 License Amendment before SONGS Unit 2 or 3 can be allowed to restart.  A permission by NRC for SONGS restart of either Unit 2 or 3 without the 50.90 License Amendment would be construed as: (1) Repeat violation of NRC 50.90 License Amendment Process by SCE, (2) Violation of SCE’s Overriding Obligation to protect the health and safety of Southern Californians from radiological accidents, and (3) Inconsistent with the NRC's long history of commitment, transparency, participation, and collaboration with the public's oversight of Nuclear Reactor regulatory activities.

-- The DAB Safety Team

Do You Live In The San Onofre Fallout Zone?
Do You Live In The San Onofre Fallout Zone?


3 comments:

  1. Excellent article (with comments) in San Diego’s KPBS.org
    Proposed Changes To San Onofre’s Decommissioning Fund
    http://is.gd/a3kWXq
    snip
    Southern California Edison and SDG&E have collected money for the fund from ratepayers over the life of the plant, to pay decommissioning costs when it ultimately shuts down.

    Electricity ratepayers have already paid more than $3 billion into the fund for San Onofre. It’s estimated that decommissioning Units 2 and 3 will cost $3.7 billion.

    PREDICTION: SORE (San Onofre Reactor Emergency) will prove to be the most expensive nuclear Debacle in the World not counting the Trillion Dollar Eco-Disaster triple meltdown in Fukushima Japan; so the question now is who will pay for it, SoCal rate payers or the shareholders of SCE and SDG&E who have had record profits every year for the past few years!

    Unless the NRC refuses to allow SCE to restart SanO, the NRC will become an accomplice to the biggest nuclear rip off the World has ever known thanks in part to the CA CPUC not doing their job by asking for a full investigation and CA Gov. Brown for "Looking the other way" while the CA CPUC fails the public's trust...

    I hope both CA Senators Feinstein and Boxer will become vocal before it is too late!

    ReplyDelete
  2. UPDATE: Salute to Donna Gilmore for sending me this
    ---------- Forwarded message ----------

    Here's the link to the ISO 9/13/2012 Press Release outlining plans for the entire year of 2013 without San Onofre.

    http://www.caiso.com/Documents/CaliforniaISOPreparesforAnotherPotentialSummerWithoutSanOnofreGeneration.pdf

    ReplyDelete
  3. Please click on the DAB Safety Team Documents tab at the top of this page for much more technical information about San Onofre!

    ReplyDelete

Thank you for your comment!